Construction Updates

Project Overview

On May 5, 2015, voters approved a $58.48 million bond referendum to address future needs of the school district. The referendum will pay for an addition and renovation to the Middle School building, renovation of the Central Education Campus building, a demolition of the 1923 portion of the Central Education Campus building, and a swimming pool addition to the Central Education Campus. Construction will begin in the spring of 2016 and continue through the start of the 2017-18 school year. (NPAS newsletter article)

Middle School Addition & Renovation

The Middle School project will add classrooms and improve safety. Updates will include the following:

Timeline (map)Description (Architect's Presentation)
Phase 1: 6 Months
March 2016 - August 2016
All work associated with demolishing the old special ed. area/entry and building the new office/secure entry as well as building the new gymnasium, fitness room, kitchen, and loading dock addition.
Phase 1A: 8 Months
May 2016 - December 2016
All work associated with adding on and renovating the art room and building the new parking lots.
Phase 1B: 10 Months
May 2016 - February 2017
All work associated with building the new classroom addition and chiller enclosure.
Phase 2: 4 Months
May 2016 - August 2016
All work associated with renovation of the instrument storage and practice rooms in the music suite.
Phase 3: 4 Months
May 2016 - August 2016
All work associated with the renovation of the following existing space: office area, locker commons, cafeteria, servery, kitchen, and fitness room areas. All work associated with replacing the window, entry systems, and metal panel around the building. All work associated with the existing roof replacement and all work associated with alternate #2.
ProjectPurpose

Classroom additions to the existing Middle School

• Provide classrooms for all 6th-8th grade students in one building.

• Improve students' safety by reducing transitions between the Central Education Campus and the Middle School.

Auxiliary gym addition

• Provide physical education space for all 6th-8th grade students in one building.

• Improve safety of students by reducing transitions between the Central Education Campus and the Middle School.

• Provide additional gym space for schools and community.

Relocate office to the front entrance

• Improve safety of students by placing office staff where they can see visitors entering the building.

Addition and renovation of the kitchen, cafeteria, and commons

• Improve and expand core spaces including the commons and cafeteria.

Deferred maintenance

• The following items will be replaced: roof, windows, and exterior doors.

• The following items will be upgraded: accessibility and electrical service.

 

Central Education Campus / Pool Addition & Renovation

The Central Education Campus project will improve learning spaces and energy efficiencies. Updates will include the following:

 Timeline (map) Description (Architect's Presentation)
Phase 1: 12 Months
May 2016 - April 2017
All work associated with the pool addition.
Phase 1A: 8 Months
May 2016 - December 2016
All work associated with the boiler room and entry addition and gymnasium roof.
Phase 1B: 5 Months
September 2016 - December 2016
All work associated with the district office renovation.
Phase 2: 4 Months
February 2017 - May 2017
All work associated with the operations department renovations.
Phase 2A: 7 Months
February 2017 - August 2017
All work associated with the remodel of former 6th grade area.
Phase 2B: 3 Months
February 2017 - April 2017
All work associated with the activities area.
Phase 2C: 2 Months
March 2017 - April 2017
All work associated with the activities entry and gymnasium.
Phase 3: 3 Months
June 2017 - August 2017
All work associated with the activities, family education, community education, and early childhood education renovations. Building new parking lots indicated. Demolition of the 1923 building.
ProjectPurpose
Demolition of the 1923 building

• Eliminate the need to maintain the deteriorating building.

• Provide additional parking spaces.

Remodel classroom spaces

• Accommodate Early Childhood programming.

• Provide multi-purpose room for schools and community.

Addition of an indoor pool and locker rooms

• Provide curriculum needs for physical fitness classes.

• Improve accommodations for the Swim and Dive team.

• Provide a zero-depth entry design provides an intergenerational facility for the entire community.

Deferred maintenance

• The following items will be replaced: roof, windows, and HVAC systems.

• The following items will be upgraded: restrooms and electrical service.

 

 

 

 

 

 

Vline.png

ConsructionsUpdates.png

News & Updates

Notice of Closed Parking Lot
(linkPick-Up/Drop-Off Info

ICS Weekly Progress Reports
(PDF) Friday, March 04, 2016
(PDF) Friday, March 11, 2016
(PDF) Friday, March 18, 2016
(PDF) Friday, March 25, 2016
(PDF) Friday, April 01, 2016
(PDF) Friday, April 08, 2016
(PDF) Friday, April 15, 2016
(PDF) Friday, April 22, 2016
(PDF) Friday, April 29, 2016
(PDF) Friday, May 06, 2016
(PDF) Friday, May 13, 2016
(PDF) Friday, May 20, 2016
(PDF) Friday, May 27, 2016
(PDF) Friday, June 03, 2016
(PDF) Friday, June 10, 2016
(PDF) Friday, June 17, 2016
(PDF) Friday, June 24, 2016
(PDF) Friday, July 01, 2016
(PDF) Friday, July 08, 2016
(PDF) Friday, July 15, 2016
(PDF) Friday, July 22, 2016
(PDF) Friday, July 29, 2016
(PDF) Friday, August 04, 2016
(PDF) Friday, August 11, 2016
(PDF) Friday, August 18, 2016
(PDF) Friday, August 25, 2016
(PDF) Friday, Sept. 02, 2016
(PDF) Friday, Sept. 09, 2016
(PDF) Friday, Sept. 16, 2016
(PDF) Friday, Sept. 23, 2016
(PDF) Friday, Sept. 30, 2016
(PDF) Friday, October 07, 2016
(PDF) Friday, October 14, 2016
(PDF) Friday, October 21, 2016
(PDF) Friday, October 28, 2016
(PDF) Friday, Nov. 04, 2016
(PDF) Friday, Nov. 11, 2016
(PDF) Friday, Nov. 18, 2016
(PDF) Friday, Dec. 02, 2016
(PDF) Friday, Dec. 09, 2016
(PDF) Friday, Dec. 16, 2016
(PDF) Friday, January 06, 2017
(PDF) Friday, January 13, 2017
(PDF) Friday, January 20, 2017
(PDF) Friday, January 27, 2017
(PDF) Friday, Feb. 03, 2017
(PDF) Friday, Feb. 10, 2017
(PDF) Friday, Feb. 17, 2017
(PDF) Friday, Feb. 24, 2017
(PDF) Friday, March 03, 2017
(PDF) Friday, March 10, 2017
(PDF) Friday, March 24, 2017
(PDF) Friday, March 31, 2017
(PDF) Friday, April 07, 2017
(PDF) Friday, April 14, 2017
(PDF) Friday, April 21, 2017
(PDF) Friday, April 28, 2017

Ground Breaking Ceremony